The critical path/TNA (Time & action) is a regular review systems to track progress of the project(s). In apparel industry the critical path/TNA (Time & action) is actually a production plan that contains a list of all activities required to be done in a time frame to ship the goods successfully within the estimated time of delivery (ETD). A smart merchandiser maintains critical path to identify the critical tasks, which if not attended to could impact delivery schedules for his styles. 
Time & Action Calendar
Buyer 
 | 
  
Li & Fung 
 | 
  
Rib Fab Content 
 | 
  
95%Ctn/5% Spandex 
 | 
 |||||
Order # 
 | 
  
JA-2376 
 | 
  
Rib Fab GSM 
 | 
  
190 GSM 
 | 
 |||||
Style  # 
 | 
  
Boys-S6 
 | 
  
Rib Consumption
  per Dz 
 | 
  
200 gm 
 | 
 |||||
Item 
 | 
  
Crew Neck Tee 
 | 
  
Total Rib Req 
 | 
  
4500 Kg 
 | 
 |||||
Body Fabric
  Content 
 | 
  
100% Ctn 
 | 
  
Yarn Count 
 | 
  
24/S 
 | 
 |||||
Body Fab
  Knitting Pattern 
 | 
  
S/J 
 | 
  
Spandex 
 | 
  
40D 
 | 
 |||||
Body Fab GSM 
 | 
  
170 GSM 
 | 
  |||||||
Gmts Ord Qty in
  pcs 
 | 
  
240000 
 | 
  
Machine Dia to
  be used 
 | 
  
24 ,28, 30, 34 
 | 
 |||||
Ord
  Confirmation Date 
 | 
  
6/8/10 
 | 
  
Yarn Count 
 | 
  
28/S 
 | 
 |||||
Del Date/ TOD 
 | 
  
6-Oct 
 | 
  |||||||
Body Fab
  Consumption per Dz 
 | 
  
3.00 Kg 
 | 
  
Finished fab
  requirement 
 | 
  
60000 Kg 
 | 
 |||||
SL 
 | 
  
Color/Qty 
 | 
  
S 
 | 
  
M 
 | 
  
L 
 | 
  
XL 
 | 
  
Total 
 | 
  ||
1 
 | 
  
Pink 
 | 
  
10000 
 | 
  
20000 
 | 
  
20000 
 | 
  
10000 
 | 
  
60000 
 | 
  ||
2 
 | 
  
Olive 
 | 
  
10000 
 | 
  
20000 
 | 
  
20000 
 | 
  
10000 
 | 
  
60000 
 | 
  ||
3 
 | 
  
Brown 
 | 
  
10000 
 | 
  
20000 
 | 
  
20000 
 | 
  
10000 
 | 
  
60000 
 | 
  ||
4 
 | 
  
Aqua Blue 
 | 
  
10000 
 | 
  
20000 
 | 
  
20000 
 | 
  
10000 
 | 
  
60000 
 | 
  ||
5 
 | 
  
Total 
 | 
  
40000 
 | 
  
80000 
 | 
  
80000 
 | 
  
40000 
 | 
  
240000 
 | 
  ||
SL# 
 | 
  
Events 
 | 
  
Action Date 
 | 
  
Remarks 
 | 
 |||||
1 
 | 
  
Cargo must be
  at Ctg Port by 
 | 
  
6-Oct 
 | 
  ||||||
2 
 | 
  
Cargo must
  leave factory not later than 
 | 
  
5-Oct 
 | 
  
Covered Van 
 | 
 |||||
3 
 | 
  
Final Insp to
  be offered not later than 
 | 
  
3-Oct 
 | 
  ||||||
4 
 | 
  
Finshing must
  be completed not later than 
 | 
  
2-Oct 
 | 
  ||||||
5 
 | 
  
All Washing (if
  any)  must be completed not later than 
 | 
  
1-Oct 
 | 
  ||||||
6 
 | 
  
All Sewing must
  be completed not later than 
 | 
  
30-Sep 
 | 
  ||||||
7 
 | 
  
Bulk Production
  as per target must be achieved not later than 
 | 
  
31-Aug 
 | 
  
All Fab &
  Accy 
 | 
 |||||
8 
 | 
  
Input should be
  given in required lines to achieve day's Target prod not later than 
 | 
  
30-Aug 
 | 
  ||||||
9 
 | 
  
Emb for day's
  prod qty must be in house not later than (if any emb) 
 | 
  
29-Aug 
 | 
  ||||||
10 
 | 
  
Printing for
  day's tgt qty must be rcvd from printing not later than 
 | 
  
28-Aug 
 | 
  ||||||
11 
 | 
  
Cutting should
  be done for required day's production as per ratio not later than 
 | 
  
27-Aug 
 | 
  ||||||
12 
 | 
  
Size-set and PP
  must be approved not later than 
 | 
  
24-Aug 
 | 
  ||||||
13 
 | 
  
All Lab-Test
  which may affect shipment to be completed not later than 
 | 
  
30-Sep 
 | 
  ||||||
14 
 | 
  
Dyed fabric as
  per size/col ratio for day's production must be delivere to cutting not later
  than 
 | 
  
26-Aug 
 | 
  ||||||
15 
 | 
  
Knitted Fabric
  for day's prod as per size color ratio must be delivered to cutting not later
  than 
 | 
  
22-Aug 
 | 
  ||||||
16 
 | 
  
Knitting for
  day's garments production (as per ratio) must start not later than 
 | 
  
19-Aug 
 | 
  ||||||
17 
 | 
  
Yarn must be at
  Factory for day's targetted qty not later than 
 | 
  
17-Aug 
 | 
  ||||||
18 
 | 
  
BB L/C for yarn
  must be opened not later than 
 | 
  
15-Aug 
 | 
  ||||||
19 
 | 
  
Master L/C must
  be received from Buyer not later than 
 | 
  
11-Aug 
 | 
  ||||||
20 
 | 
  
Color Standard
  Must be received not later than 
 | 
  
7-Aug 
 | 
  ||||||
21 
 | 
  
First Labdip to
  be submitted not later than 
 | 
  
10-Aug 
 | 
  ||||||
22 
 | 
  
Product package
  must be received not later than 
 | 
  
7-Aug 
 | 
  ||||||
23 
 | 
  
Proto Sample
  must be submitted not later than (with available Fabric) 
 | 
  
8-Aug 
 | 
  ||||||
24 
 | 
  
All Accessories
  Development must be completed and approved not later than 
 | 
  
16-Aug 
 | 
  ||||||
25 
 | 
  
All Accessories
  must be at Factory not later than 
 | 
  
27-Aug 
 | 
  ||||||
26 
 | 
  
All washing
  approval  (if any) must be obtained by 
 | 
  
2-Sep 
 | 
  ||||||
27 
 | 
  
Sewing and
  Thread Must be at Factory by 
 | 
  
28-Aug 
 | 
  ||||||



ghh yks h hht jhf gt j fdg g j gh
ReplyDeletetanxs 4 hardly cooperation.................
ReplyDeleteThe Le_Meridian Funding Service went above and beyond their requirements to assist me with my loan which i used expand my pharmacy business,They were friendly, professional, and absolute gems to work with.I will recommend anyone looking for loan to contact. Email..lfdsloans@lemeridianfds.com Or lfdsloans@outlook.com.WhatsApp ... + 19893943740.
ReplyDeleteGet More Info high replica bags read here cheap designer bags replica his comment is here bag replica high quality
ReplyDeletego to the website hop over to this website a knockout post you can try this out get more original site
ReplyDeletereplica bags london Click This Link b9i96s3m87 replica bags prada her explanation r0p97d8y31 best replica bags online replica bags in uk replica bags lv hermes replica q8l12b3c44 replica bags and watches
ReplyDelete