Saturday, August 31, 2013

Critical Path/TNA

The critical path/TNA (Time & action) is a regular review systems to track progress of the project(s). In apparel industry the critical path/TNA (Time & action) is actually a production plan that contains a list of all activities required to be done in a time frame to ship the goods successfully within the estimated time of delivery (ETD). A smart merchandiser maintains critical path to identify the critical tasks, which if not attended to could impact delivery schedules for his styles. 

Please find below sample critical path/TNA sheets for reference.



























Time & Action Calendar
Buyer
Li & Fung
Rib Fab Content
95%Ctn/5% Spandex
Order #
JA-2376
Rib Fab GSM
190 GSM
Style  #
Boys-S6
Rib Consumption per Dz
200 gm
Item
Crew Neck Tee
Total Rib Req
4500 Kg
Body Fabric Content
100% Ctn
Yarn Count
24/S
Body Fab Knitting Pattern
S/J
Spandex
40D
Body Fab GSM
170 GSM
Gmts Ord Qty in pcs
240000
Machine Dia to be used
24 ,28, 30, 34
Ord Confirmation Date
6/8/10
Yarn Count
28/S
Del Date/ TOD
6-Oct
Body Fab Consumption per Dz
3.00 Kg
Finished fab requirement
60000 Kg
SL
Color/Qty
S
M
L
XL
Total
1
Pink
10000
20000
20000
10000
60000
2
Olive
10000
20000
20000
10000
60000
3
Brown
10000
20000
20000
10000
60000
4
Aqua Blue
10000
20000
20000
10000
60000
5
Total
40000
80000
80000
40000
240000
SL#
Events
Action Date
Remarks
1
Cargo must be at Ctg Port by
6-Oct
2
Cargo must leave factory not later than
5-Oct
Covered Van
3
Final Insp to be offered not later than
3-Oct
4
Finshing must be completed not later than
2-Oct
5
All Washing (if any)  must be completed not later than
1-Oct
6
All Sewing must be completed not later than
30-Sep
7
Bulk Production as per target must be achieved not later than
31-Aug
All Fab & Accy
8
Input should be given in required lines to achieve day's Target prod not later than
30-Aug
9
Emb for day's prod qty must be in house not later than (if any emb)
29-Aug
10
Printing for day's tgt qty must be rcvd from printing not later than
28-Aug
11
Cutting should be done for required day's production as per ratio not later than
27-Aug
12
Size-set and PP must be approved not later than
24-Aug
13
All Lab-Test which may affect shipment to be completed not later than
30-Sep
14
Dyed fabric as per size/col ratio for day's production must be delivere to cutting not later than
26-Aug
15
Knitted Fabric for day's prod as per size color ratio must be delivered to cutting not later than
22-Aug
16
Knitting for day's garments production (as per ratio) must start not later than
19-Aug
17
Yarn must be at Factory for day's targetted qty not later than
17-Aug
18
BB L/C for yarn must be opened not later than
15-Aug
19
Master L/C must be received from Buyer not later than
11-Aug
20
Color Standard Must be received not later than
7-Aug
21
First Labdip to be submitted not later than
10-Aug
22
Product package must be received not later than
7-Aug
23
Proto Sample must be submitted not later than (with available Fabric)
8-Aug
24
All Accessories Development must be completed and approved not later than
16-Aug
25
All Accessories must be at Factory not later than
27-Aug
26
All washing approval  (if any) must be obtained by
2-Sep
27
Sewing and Thread Must be at Factory by
28-Aug



6 comments:

  1. ghh yks h hht jhf gt j fdg g j gh

    ReplyDelete
  2. tanxs 4 hardly cooperation.................

    ReplyDelete
  3. The Le_Meridian Funding Service went above and beyond their requirements to assist me with my loan which i used expand my pharmacy business,They were friendly, professional, and absolute gems to work with.I will recommend  anyone looking for loan to contact. Email..lfdsloans@lemeridianfds.com  Or lfdsloans@outlook.com.WhatsApp ... + 19893943740.

    ReplyDelete
  4. replica bags london Click This Link b9i96s3m87 replica bags prada her explanation r0p97d8y31 best replica bags online replica bags in uk replica bags lv hermes replica q8l12b3c44 replica bags and watches

    ReplyDelete

Popular Posts