The critical path/TNA (Time & action) is a regular review systems to track progress of the project(s). In apparel industry the critical path/TNA (Time & action) is actually a production plan that contains a list of all activities required to be done in a time frame to ship the goods successfully within the estimated time of delivery (ETD). A smart merchandiser maintains critical path to identify the critical tasks, which if not attended to could impact delivery schedules for his styles.
Time & Action Calendar
Buyer
|
Li & Fung
|
Rib Fab Content
|
95%Ctn/5% Spandex
|
|||||
Order #
|
JA-2376
|
Rib Fab GSM
|
190 GSM
|
|||||
Style #
|
Boys-S6
|
Rib Consumption
per Dz
|
200 gm
|
|||||
Item
|
Crew Neck Tee
|
Total Rib Req
|
4500 Kg
|
|||||
Body Fabric
Content
|
100% Ctn
|
Yarn Count
|
24/S
|
|||||
Body Fab
Knitting Pattern
|
S/J
|
Spandex
|
40D
|
|||||
Body Fab GSM
|
170 GSM
|
|||||||
Gmts Ord Qty in
pcs
|
240000
|
Machine Dia to
be used
|
24 ,28, 30, 34
|
|||||
Ord
Confirmation Date
|
6/8/10
|
Yarn Count
|
28/S
|
|||||
Del Date/ TOD
|
6-Oct
|
|||||||
Body Fab
Consumption per Dz
|
3.00 Kg
|
Finished fab
requirement
|
60000 Kg
|
|||||
SL
|
Color/Qty
|
S
|
M
|
L
|
XL
|
Total
|
||
1
|
Pink
|
10000
|
20000
|
20000
|
10000
|
60000
|
||
2
|
Olive
|
10000
|
20000
|
20000
|
10000
|
60000
|
||
3
|
Brown
|
10000
|
20000
|
20000
|
10000
|
60000
|
||
4
|
Aqua Blue
|
10000
|
20000
|
20000
|
10000
|
60000
|
||
5
|
Total
|
40000
|
80000
|
80000
|
40000
|
240000
|
||
SL#
|
Events
|
Action Date
|
Remarks
|
|||||
1
|
Cargo must be
at Ctg Port by
|
6-Oct
|
||||||
2
|
Cargo must
leave factory not later than
|
5-Oct
|
Covered Van
|
|||||
3
|
Final Insp to
be offered not later than
|
3-Oct
|
||||||
4
|
Finshing must
be completed not later than
|
2-Oct
|
||||||
5
|
All Washing (if
any) must be completed not later than
|
1-Oct
|
||||||
6
|
All Sewing must
be completed not later than
|
30-Sep
|
||||||
7
|
Bulk Production
as per target must be achieved not later than
|
31-Aug
|
All Fab &
Accy
|
|||||
8
|
Input should be
given in required lines to achieve day's Target prod not later than
|
30-Aug
|
||||||
9
|
Emb for day's
prod qty must be in house not later than (if any emb)
|
29-Aug
|
||||||
10
|
Printing for
day's tgt qty must be rcvd from printing not later than
|
28-Aug
|
||||||
11
|
Cutting should
be done for required day's production as per ratio not later than
|
27-Aug
|
||||||
12
|
Size-set and PP
must be approved not later than
|
24-Aug
|
||||||
13
|
All Lab-Test
which may affect shipment to be completed not later than
|
30-Sep
|
||||||
14
|
Dyed fabric as
per size/col ratio for day's production must be delivere to cutting not later
than
|
26-Aug
|
||||||
15
|
Knitted Fabric
for day's prod as per size color ratio must be delivered to cutting not later
than
|
22-Aug
|
||||||
16
|
Knitting for
day's garments production (as per ratio) must start not later than
|
19-Aug
|
||||||
17
|
Yarn must be at
Factory for day's targetted qty not later than
|
17-Aug
|
||||||
18
|
BB L/C for yarn
must be opened not later than
|
15-Aug
|
||||||
19
|
Master L/C must
be received from Buyer not later than
|
11-Aug
|
||||||
20
|
Color Standard
Must be received not later than
|
7-Aug
|
||||||
21
|
First Labdip to
be submitted not later than
|
10-Aug
|
||||||
22
|
Product package
must be received not later than
|
7-Aug
|
||||||
23
|
Proto Sample
must be submitted not later than (with available Fabric)
|
8-Aug
|
||||||
24
|
All Accessories
Development must be completed and approved not later than
|
16-Aug
|
||||||
25
|
All Accessories
must be at Factory not later than
|
27-Aug
|
||||||
26
|
All washing
approval (if any) must be obtained by
|
2-Sep
|
||||||
27
|
Sewing and
Thread Must be at Factory by
|
28-Aug
|